METRO will open for passenger operation
in December 2008.
|
Operations and Maintenance Center
|
Completed ahead of schedule. Opened in 2007.
|
|
Town Lake Bridge
|
Structure completed in August 2006, ahead of schedule
|
|
Line Section 4
|
Civil construction was completed in December 2007. Continuing systems work will not affect roadways.
|
|
Line Section 2
|
Civil construction is scheduled for completion in early summer 2008.
|
|
Line Section 3
|
Civil construction is scheduled for completion in winter 2008.
|
|
Line Section 1
|
Civil construction is scheduled for completion in late summer 2008. Continuing systems work will not affect roadways or business access.
|
|
Line Section 5
|
Civil construction is set for completion in March 2008. Major roadwork is already finished.
|