Construction Schedule

METRO will open for passenger operation in December 2008.

Completion Schedule

Operations and Maintenance CenterCompleted ahead of schedule. Opened in 2007.
Town Lake BridgeStructure completed in August 2006, ahead of schedule
Line Section 4Civil construction was completed in December 2007. Continuing systems work will not affect roadways.
Line Section 2Civil construction is scheduled for completion in early summer 2008.
Line Section 3Civil construction is scheduled for completion in winter 2008.
Line Section 1Civil construction is scheduled for completion in late summer 2008. Continuing systems work will not affect roadways or business access.
Line Section 5Civil construction is set for completion in March 2008. Major roadwork is already finished.