Providing Public Transportation
Alternatives for the Greater
Phoenix Metro Area

Contact:

Debra Boehlke
Community Outreach Coordinator
602.697.4913
Email

Documents


Project Details

Status:Study/Planning
Region:Northwest Valley
Type:Extensions/New Service

Contact:

Amanda Luecker
Project Manager
602.495.8241
Email

Public Meetings

Fiesta District Public Meeting
October 26, 2017
5:30-7:30 p.m.
Mesa Police Department
Fiesta Division Community Room
1010 West Grove Avenue, Mesa


Documents


Project Details

Status:Study/Planning
Region:East Valley
Type:Extensions/New Service

Contact:

Terry Gruver
Community Outreach Coordinator
602.744.5546
Email

Contact:

Dolores Nolan
Community Relations Coordinator
602.523.6070
Email

Documents


Project Details

Status:Completed
Region:Southeast Valley
Type:Extensions/New Service

Documents


Project Details

Status:Study/Planning
Region:West Valley, Southwest Valley
Type:Extensions/New Service

Contact:

Bob Antila
Senior Management Analyst
602.523.6038
Email

Documents


Project Details

Status:Completed
Region:Northeast Valley
Type:Extensions/New Service

Documents


Project Details

Status:Study/Planning
Region:West Valley, Central Valley, East Valley
Type:Extensions/New Service

Contact:

Dawn M. Coomer
TDM Manager
602.523.6053
Email

Documents


Project Details

Status:Completed
Region:Southeast Valley
Type:Extensions/New Service

Contact:

Sonya Pastor La Sota
Community Outreach Coordinator
602.744.5584
Email

Feedback Form
Forma des Opiniones

Documents


Project Details

Status:Study/Planning
Region:Central Valley
Type:Extensions/New Service

Contact:

Lisa Saldin
Community Outreach Coordinator
602.495.8213
Email

Documents


Project Details

Status:Study/Planning
Region:Central Valley
Type:Extensions/New Service

Contact:

Dolores Nolan
Community Outreach Coordinator
602.523.6070
Email

Documents


Project Details

Status:Study/Planning
Region:East Valley
Type:Extensions/New Service
Fund Source:American Recovery and Reinvestment Act

Contact:

Lisa Saldin
Community Outreach Coordinator
602.495.8213
Email

Contact:

Jordan Brackett
Community Outreach Coordinator
602.744.5552
Email

Mary Ann Miller
Business Assistance Coordinator
480.468.3620
Email

Documents


Project Details

Status:Study/Planning
Region:Central Valley, West Valley
Type:Extensions/New Service

Contact:

Sonya Pastor La Sota
Community Outreach Coordinator
602.744.5584
Email

Documents


Project Details

Status:Study/Planning
Region:West Valley
Type:Extensions/New Service

Contact:

Terry Gruver
Community Outreach Coordinator
602.744.5546
Email

Documents


Project Details

Status:Study/Planning
Region:Northeast Valley
Type:Extensions/New Service

Contact:

Lisa Saldin
Community Outreach Coordinator
602.495.8213
Email

Documents


Project Details

Status:Completed
Progress:
Region:Central Valley
Type:Extensions/New Service

Contact:

Jorge Llamas
Business Assistance Coordinator
602.523.6067
Email

Traffic Restrictions

Public Meetings

Community Celebration on the Gilbert Road Extension
October 21, 2017
9-11 a.m
815 E. Main St., Mesa


Documents


Project Details

Status:Under Construction
Progress:
Region:East Valley
Type:Extensions/New Service

Contact:

Michael Book
Community Outreach Coordinator
602.256.5811
Email

Documents


Project Details

Status:Study/Planning
Type:Extensions/New Service

Contact:

Julie Cruz Gilfillan
Community Outreach Coordinator
602.495.8274 jcruz@valleymetro.org
Email

Documents


Project Details

Status:Completed
Progress:
Region:East Valley
Type:Extensions/New Service

Contact:

Rob Antoniak
Community Outreach Coordinator
602-495-8209
Email

Documents


Project Details

Status:In Process
Progress:
Region:East Valley
Type:[5405] Extensions - extensions
Fund Source:Proposition 400, Federal Transit Administration

Contact:

Rob Antoniak
Community Outreach Coordinator
602 495-8209, Cell: 602 369-3681
Email

Gary Flunoy
Business Assistance Specialist
602 322-4457, Cell: 602 291-7670
Email

Public Meetings


Documents


Project Details

Status:Planning Stage
Progress:
Region:Central Valley, West Valley
Type:[3880] Express Bus Route - express_bus_route [5405] Extensions - extensions [3883] Park-and-Ride - park-and-ride
Fund Source:Federal Transit Administration, Proposition 400, American Recovery and Reinvestment Act

Contact:

Chris Basnight
Owner
919-123-1234
Email

Christine Basnight
HR
919-123-2345
Email

Documents


Project Details

Status:Completed
Progress:
Region:East Valley
Type:Facilities
Fund Source:Proposition 400

Contact:

Robert Yabes
City of Tempe
(480) 350-2734
Email

Documents


Project Details

Status:Completed
Region:West Valley, Central Valley
Type:Facilities
Fund Source:Federal Transit Administration

Contact:

Kini Knudson
City of Phoenix
(602) 262-7254
Email

Documents


Project Details

Status:Study/Planning
Region:East Valley
Type:Extensions/New Service
Fund Source:Proposition 400, Federal Transit Administration

Contact:

Lisa Saldin
(602) 495-8213
Email

Documents


Project Details

Status:Completed
Progress:
Region:Central Valley
Type:Facilities
Fund Source:American Recovery and Reinvestment Act

Contact:

Kini Knudson
City of Phoenix
(602) 262-7254
Email

Documents


Project Details

Status:Completed
Progress:
Region:East Valley
Type:Facilities
Fund Source:Proposition 400, Federal Transit Administration

Contact:

Rob Antoniak
(602) 495-8209
Email

Documents


Project Details

Status:Study/Planning
Region:West Valley
Type:Facilities

Contact:

Omar J. Peters
Project Manager
602.744.5557
Email

Documents


Project Details

Status:Study/Planning
Region:East Valley
Type:Facilities
Fund Source:Proposition 400

Contact:

Stuart Boggs
Planning Manager
602-523-6039
Email

Documents


Project Details

Status:Completed
Region:East Valley
Type:Facilities
Fund Source:Proposition 400

Documents


Project Details

Status:Completed
Region:West Valley
Type:Facilities
Fund Source:Proposition 400

Public Meetings


Documents


Project Details

Status:Completed
Region:East Valley
Type:Facilities
Fund Source:American Recovery and Reinvestment Act

Documents


Project Details

Status:Planning Stage
Region:East Valley
Type:[3884] Facilities - facilities

Documents


Project Details

Status:Completed
Region:West Valley
Type:Facilities
Fund Source:Proposition 400

Documents


Project Details

Status:Completed
Progress:
Region:East Valley
Type:Facilities
Fund Source:Proposition 400

Documents


Project Details

Status:Completed
Region:East Valley
Type:Extensions/New Service
Fund Source:Proposition 400, American Recovery and Reinvestment Act

50th Street Station

50th Street Station

Status

Construction on the 50th St/Washington Valley Metro Rail station began on June 8, 2017.

Safety tips in construction zones:

  • Be alert around construction
  • Allow for extra travel time
  • Always use designated crosswalks
  • Limit distractions such as cell phones and headphones

Background

The first new station along the existing Valley Metro Rail system will serve the communities and future development near 50th Street and Washington. The station will provide access to the Ability360 facility and the neighboring business community, as well as support transit-oriented development planned for the area. Ability360 offers and promotes programs designed to empower people with disabilities to take personal responsibility so that they may achieve or continue independent lifestyles within the community.

View the city of Phoenix PHXTV update on the new station.

The station will be a model of increased accessibility with design elements incorporated as a result of the PHX Innovation Games challenge issued by the City of Phoenix Mayor’s Office. The station designer is working with Innovation Games winner, Dig Studio, on station access, aesthetics and station entry areas.  Artist Barbara Grygutis is creating the art for the station.

The 50th Street Station is the first light rail project slated under Phoenix Transportation 2050 (T2050).

Business Assistance

Valley Metro and the city of Phoenix have dedicated professionals to help residents and businesses through construction. A custom business assistance program also provides resources to help businesses within the project area stay well-positioned during construction.

View 50th St. Station Business Assistance Brochure

Timeline:

Event Schedule
Design Late 2016-mid 2017
Construction Mid 2017-mid 2019
Opening Mid 2019