Providing Public Transportation
Alternatives for the Greater
Phoenix Metro Area

Northwest Phase I

Northwest Phase I

Valley Metro’s Northwest Extension is an expansion of light rail service that will eventually travel to the area near Interstate 17 and Dunlap Avenue.  Phase I of the construction project is a 3.2-mile extension that will extend light rail north on 19th Avenue from Montebello to Dunlap Avenue and serve 5,000 riders per day. Construction began in January 2013.

The Northwest Extension include three stations, one park-and-ride and connections to bus service at Bethany Home Road, Glendale, Northern and Dunlap avenues. This extension is scheduled to open in late 2015/early 2016 and will support nearly 20,000 residents and another 20,000 employees.  It will serve as an essential means of travel in an area where 14 percent of households are dependent on transit compared to seven percent countywide.

Originally scheduled to open in 2012, the Northwest Extension was placed on hold due to the economic downturn and the completion date was revised to 2023.  In 2012, the Phase I of the project received approval to move ahead utilizing capital funds from the countywide Proposition 400 transit sales tax, as well as funds from Phoenix’s Transit 2000.  Phoenix is responsible for the operations costs of light rail service that travels in their city.

Phase II of the project will eventually expand light rail service west towards I-17.  It is currently slated for opening in 2026.  Alternative funding options will be sought to accelerate this phase.

Status

Construction of the Northwest Extension began in January 2013. The construction contractor, Sundt/Stacy & Witbeck Joint Venture, and the third party utility companies have completed relocating all of the utilities along 19th Avenue such as water, gas and power lines. 

Rail delivery occurred in September 2013 and roadway widening began in early 2014 and will be followed by guide way installation. Rail welding occurred summer 2014 and the project celebrated the First Track installation in July 2014. Track installation has occurred at the site of the future park-and-ride at Dunlap Avenue and is continuing down 19th Avenue. 

Location is Nearby

19th Avenue, Bethany Home Road – Dunlap Avenue

Timeline:

Event Schedule
Utility Relocation Winter 2013 - Fall 2014
Roadway Widening Summer 2013 - Summer 2015
Track/Station Installation Winter 2014 - Fall 2015
Light Rail Testing/Operations Fall 2015 - Winter 2016


   !