Northwest Phase II

Northwest Phase II

Status

The Northwest Phase II Extension is advancing to the next phase of design. In September, the Valley Metro Board of Directors approved Kiewit - McCarthy as the project’s construction contractor. Valley Metro is also preparing the federally-required Environmental Assessment (EA), which evaluates the potential impacts to the neighboring environment including noise, vibration, and traffic. 

Next Steps

Community outreach is ongoing, and the public will have the opportunity to review and comment on the EA as well as the design plans in early 2018.

Background

In 2004, the Phoenix City Council approved the Northwest Light Rail Extension, which included 4.6 miles of additional light rail service, extending from the previous end-of-line at 19th Ave. and Montebello Ave. to 25th Ave. and Mountain View Rd. In 2007, the route was divided into two phases. The 3.2-mile Phase I on 19th Ave. from Montebello to Dunlap Ave. opened on March 19, 2016.

Phase II of the project will extend west on Dunlap Ave., north on 25th Ave. and across I-17 near Mountain View Rd. with a terminus on the west side of the freeway near Metrocenter Mall. The Phoenix City Council approved the I-17 crossing in 2014.

In January 2016, the Phoenix City Council approved accelerating segments of the future high-capacity/light rail transit system. With the acceleration, Northwest Phase II will open in 2023, three years earlier than previously planned.

Timeline:

Event Schedule
Planning 2015-2017
Design 2017-2019
Construction 2019-2023
Opening 2023


-->